A 1952 Normal Heights Gut Renovation: The Pre-Construction Difference
A homeowner in Normal Heights came to me with a house built in 1952. They had a plan to renovate every single room.
During our initial walk-through, I noticed a slight sag in the center hallway. Before finalizing any design plans or pulling permits, we brought in our structural engineer. We discovered the original footing was resting on uncompacted fill. We also identified a load-bearing wall separating the kitchen from the living space.
The structural engineer confirmed the wall could come out with a beam header and two posts. More importantly, we flagged the foundation issue as a primary risk during pre-construction. We engineered a localized underpinning solution and included it in the initial permit application.
Because we identified this before demolition, the contingency budget covered the foundation fix without altering the overall project timeline. We didn't have to stop work for four weeks to pull a revision permit.
That is the difference between a managed whole-home gut renovation and a reactive one.
Joseph Sheiner, Founder